| <<
back to projects I
1 I 2
I |
|
| |
| Subsea
Pipelay Handling System... |
| |
| The
Statoil
Kristin Project in 2004 (carried out by Technip)
required laying of 10" subsea pipe with simultaneous
fixing of a piggyback heating cable onto the pipe during the
lay operation.
In order
to fix the cable to the pipe and provide supplementary subsea
protection it was also necessary to install heavy duty plastic
conduit banded to the pipe during the pipe lay operation.
This difficult procedure required a custom designed handling
system for transportation of the conduit from the storage
area up to a new platform on the top of the pipe ramp and
to semi-automate conduit installation onto the cable/pipe. |
| |
|
|
|
 |
Working
closely with the naval architects and mechanical designers
of the system, Melbourne
Marine Services we designed, supplied, installed and
commissioned the materials handling automation and drive
systems for the entire equipment spread.
With many technical issues to overcome the project was probably
our most ambitious to date.
|
| |
|
|
|
The
equipment package included:-
|
|
|
|
- Variable
speed AC drive systems for the horizontal conveyor &
gantry lift elevator.
- Electrically
powered constant tension roller box for conduit assembly.
- RF
telemetry linked cable tension monitoring system.
- Ancillary
pneumatic & hydraulic handling equipment design.
|
|
 |
| |
|
|
|
 |
All
of the equipment was fully designed, built and tested in house
before shipping to Technip-Coflexip’s Orkanger Spoolbase
in Norway.
Installation and pre-commissioning at the Vigor
construction yard took place over a number of trips before
final mobilization onto CSO Apache. |
| |
|
|
|
Trials
of the final system yielded impressive results with combined
pipe/cable lay speeds of up to 400m/hour being achieved.
The performance
figures met and exceeded the original design specification.
|
|
|
 |
| |
|
|
|
| <<
back to projects I
1 I 2
I |
| |
| |