Operating
in the marine and offshore industry we're used to working
to impossibly tight deadlines.
When a fire in the emergency generator compartment of one
of our customers vessels rendered it inoperable we were asked
to assist with urgent repairs.
Within
3 weeks we had designed, submitted drawings to class for approval,
built and tested the replacement emergency generator switchboard.
Working double shifts, we managed to complete the switchboard
build within 6 working days from receipt of the materials
and equipment to being ready for final testing and approval.
A comprehensive range of in-house testing and inspection was
then carried out prior to attendance of the Lloyd's
Register of Shipping surveyor who then inspected and witnessed
the following: |